Recently, the 22KV substation in the Central Utility Complex (CUC) is successfully energized for the first time. This marks the beginning of the CUC pulsates electricity and power transmission in the New Capital CBD project, ensuring the incoming joint commissioning and testing of CUC power devices.
As the second largest Central Utility Complex in Egypt, the CUC in the New Capital CBD Project covers a construction area of 26,000 square meters and a total area of 40,500 square meters. It includes refrigeration plant room, cold storage tank, emergency generator room, laundry room, humidification water and irrigation tank, etc. These functional structures, also knownas the heart of the CBD project, provide chilled water, emergency power, domestic water, fire-fighting water and irrigation water to the 20 towers in the New Capital CBD Project.