Recently, various construction projects by CSCEC have accelerated their progress, successfully hitting new milestones.
KPS Office Building in Sihanoukville topped out
The main structure of the tower in the KPS Office Building project in Sihanoukville, Cambodia, has been successfully topped out.
Located in Cambodia's second-largest city and biggest seaport, Sihanoukville, the project covers a total area of 75,000 square meters. It includes two towers, an entertainment center, and surrounding outdoor facilities. The twin towers rise to a height of 88 meters. Upon completion, the project will significantly enhance the infrastructure and service capabilities of Sihanoukville.
Phase II C3 office building of the Polygroup Project in Indonesia topped out
The Phase II C3 office building of the Polygroup Project in Indonesia has been topped out, marking the transition to the decoration and electromechanical installation stage, and achieving a key project milestone.
Located in the Kendal Industrial Park - Central Java, Indonesia, it is the largest industrial factory undertaken by CSCEC in Indonesia, with a total building area of approximately 306,700 square meters. The project is divided into four phases and includes 26 buildings.
Phase 5 project of the Chindata Group data center successfully completed energization
Recently, the Phase 5 project of the Chindata Group data center in Malaysia successfully completed the energization of its medium-voltage cabinet.
Located in Johor, Malaysia, the completion of the Qinhuai Data Center Phase V will deliver superior data center solutions to its clients.